Skip to content
7:00am – 7:00pm, seven days
NL-4428CurrambineApril 2026

7kW charger on a board with no room left

The charger was the easy part. The interesting part was finding out, before anything was ordered, that the board could not take it.

Filed under EV chargers.

Suburb
Currambine
Job
7kW charger, dedicated circuit
Cable run
24 m, part underground
Board
Extended, 4 spare ways left
On site
One day
Solar
Excess-solar charging enabled
CurrambineNL-4428
Schematic of an electric vehicle charger — a dedicated circuit from the switchboard, along the wall in conduit, to a 7.4 kilowatt wall unit and its lead into the car's charge port.7.4kW

What happened

The call

A new car was arriving in eleven days. The dealer had passed on a charger quote that started with the word 'from', and the owner wanted to know what the real number was before the car turned up and became a problem.

The parking spot was on the opposite side of the house from the switchboard, with a paved side path in between. That was the part the owner already suspected would cost money. It was not the part that did.

What we found

The assessment that changed the plan

The board was a 2004 unit, full. Every way occupied, no room for another breaker, and no space in the enclosure to extend it neatly. Landing a 32-amp continuous load anywhere on it was not going to happen compliantly.

The supply itself was fine — 63 amp single phase with plenty of headroom for another 32-amp circuit once the aircon and the oven were accounted for. So this was a board problem, not a supply problem, which is a considerably cheaper problem to have.

We quoted a matched extension enclosure beside the existing board rather than a full replacement, which kept the cost down and left four spare ways for whatever comes next.

What we did
  • Load assessment on the existing supply, written up before anything was ordered
  • Matched extension enclosure fitted alongside the existing board, four spare ways left
  • 24 metre run: surface conduit through the roof space, then buried in conduit under the side path
  • 7kW wall charger mounted at the parking spot, positioned for a driver's-side port
  • Dedicated RCBO with type B residual current protection as the charger requires
  • Charger paired to the inverter for excess-solar charging, plus an off-peak fallback schedule
How it ended

The car arrived eight days later to a charger that was already commissioned and tested, on a circuit sized for continuous load rather than for the minimum that would pass.

The load assessment is the part worth repeating. Ninety minutes on site before anything was ordered turned a potential board replacement into a board extension, and the owner knew the real figure a week and a half before the car did.

Job ticketNL-4428
  1. Load assessment

    Supply, existing load and board space checked. Fixed price issued that evening.

  2. Arrived, set out the run

    Route walked with the owner and the trench line marked along the side path.

  3. Extension enclosure fitted

    New enclosure mounted and linked, with a short outage of about forty minutes.

  4. Cable run through the roof

    Roof space section installed and clipped, dropped down the external wall in conduit.

  5. Underground section

    Trenched, conduit laid, warning tape over it, pavers reinstated the way we found them.

  6. Charger mounted and terminated

    Unit fitted at the parking spot, circuit landed on its own type B RCBO.

  7. Commissioned with the owner

    App set up, solar matching enabled, off-peak schedule set as a fallback.

  8. Tested and certified

    Full test sequence, certificate issued, and the car charged before we left.

What they said afterwards

  • 5 out of 5

    Two other sparkies quoted the charger off a photo of my meter box. Northline came out, spent an hour and a half working out what my board could actually carry, and gave me one number that did not move. Car turned up a week later and it just worked.

    Sam K.Currambine · April 2026Read the job this refers to

No power right now

Tell us what it is doing and we will tell you what it costs.

We text when we are on the way, and you get the price before we start.

7:00am – 7:00pm, seven days · EC 13927